Extended Scope of Work/Notes:
|
(MP3) WEST COUNTY WASTEWATER DISTRICT- PROJECT #14LS407, VARIOUS LIFT STATION UPGRADE PROJECT.
(MP3) COST DOES NOT INCLUDE WEEKEND OR OVERTIME WORK.
3-9-2020: PER MR. BERMUDEZ, THIS PERMIT HAS BEEN ADJUSTED TO REFLECT 120 DAYS VS 245 DAYS, ORIGINALLY SUBMITTED. PLEASE NOTE THAT FEES HAVE BEEN ADJUSTED.
SHOULD THIS JOB ENTAIL ADDITIONAL TIME, THE CONTRACTOR WILL BE BILLED SEPARATELY.
(PH) CONTRACTOR HAD DELAY IN WORK DUE TO COVID 19. EXTENSION GRANTED PER Y. BERMUDEZ, FOR 120 DAYS. EXTENSION FEE INCLUDED. INSPECTIONS CAN BE APPLIED FROM ORIGINAL FEES.
|