Extended Scope of Work/Notes:
|
(MP3) WORK CREW TO TRENCH +/- 83 L.F AND BORE +/- 1427 LF FOR TOTAL OF +/- 1510 LFF TO INSTALL CONDUIT FOR THE PURPOSE OF PLACING AND SPACING NEW FIBER OPTIC CABLE. WILL PLACE 6 NEW UNDERGROUND VAULTS. WORK CREW WILL REMOVE AND REPLACE +/- 465 SQFT OF CONCRETE AND +/- 180 SQFT ASPHALT. WILL SET UP CORRESPONDING TRAFFIC CONTROL PER CITY OF RICHMOND STANDARDS. WORK SET TO BEGIN 1/20/2020.
(MP3) EXTENSION GRANTED PER P. HAMPTON 3/16/20, EXTENSION FEE $501.00 NOW DUE.
(DR2) WE HAVE FIBER IN THE AREA OF WORK. WE WILL NEED 48 HOURS OF DRY WEATHER TO USA OUR FIBER. CONTRACTOR TO CALL MONROE 48 HR OF DRY WEATHER TO USA THE CITY FIBER PRIOR TO CONSTRUCTION STARTING. MONROE HARRISON 510-714-7666 IT DEPARTMENT.
(PH) DUE TO COVID-19, SPECIAL EXTENSION DATE IS GRANTED THRU 7-1-2020.
|