Extended Scope of Work/Notes:
|
SITE UTILITY SUBCONTRACTOR WILL EXCAVATE AND INSTALL TRASH CAPTURE DEVICE ON CORNER OF 13TH STREET AND BARRET. SUBCONTRACTOR WILL THEN EXCAVATE AND INSTALL NEW STORM DRAIN FROM THE CORNER OF 13TH STREET AND BARRET, DOWN 13TH STREET.
(RC3) TRAFFIC CONTROL SHALL MAINTAIN MIN 10' LANES.
(RC3) REVISIONS: Work Description: Joint Trench subcontractor will demo, excavate and trench for running power from PG&E primary vault located on Marina way into the construction site. Additionally, on 13th street, the subcontractor is to demo, excavate and trench for joint trench from AT&T pole to the construction site.
(RC3) EXTENSION APPROVED; RC
NO CHANGE IN SCOPE OF WORK OR DAYS WORKING IN PUBLIC RIGHT-OF-WAY
|